Transfer/Shifting of service connection/deviation of lines and shifting of Equipment :
      The transfer of service connection shall be affected within 15 days from the date of receipt of complete application. The service connection from the name of a person to the name of another consumer shall not be transferred unless the arrear charges pending against the previous occupier are cleared.
      Wherever the consumers request for shifting the service connection to the new premises or for deviation for the existing lines at their cost the following time schedule shall be observed for completing these works after getting the expenses as laid down in this Code.

  • 1. Shifting of meter/service 15 days
  • 2. Shifting of LT lines 30 days
  • 3. Shifting of 11KV lines 60days
  • 4. Shifting of 33KV lines 90days
  • 5. Shifting of 33/11 KV Distribution Transformer structures 90 days
      The time schedule given above includes the time required for preparation of estimates, collection of deposits, etc.
      The accounts should be settled within three months from the date of completion of shifting work by recovery of excess expenditure or refunding the balance deposit.

  

 
 
  North Eastern Electricity Supply Company of Orissa Ltd.
Corporate Office: At:Januganj, Balasore, Pin:756019,
Phone:(06782)-269864 Fax No:(06782)-263259
E-mail Id :nescoltd@hotmail.com ,
nescoltd@rediffmail.com, nesco@nescoorissa.com
Copyright © 2007 NESCO Powered By: ORISSADISCOMS CSO-IT